Names the $660-690B aggregate 2026 hyperscaler capex range (vs ~$380B 2025) with per-company breakdown; hyperscalers now supply-constrained not demand-constrained; power flagged as the binding deployment constraint

AI Capex 2026 — The $690B Infrastructure Sprint

Core Thesis

The five largest US cloud/AI infrastructure providers (Amazon, Microsoft, Alphabet, Meta, Oracle) are collectively guiding to $660–690B in 2026 capex, roughly doubling 2025's ~$380B — and management commentary across the group is now "supply-constrained," not "demand-constrained."

Per-Company 2026 Capex Guidance

Company2026 CapexNotable Detail
Amazon$200BMajority to data centers; CEO says AI capacity monetizes as fast as it installs
Alphabet$175–185BRevised upward three times from an initial $71–73B projection; cloud backlog +55% to $240B
Microsoft$120B+$37.5B spent in the most recent quarter alone; ~$80B unfulfilled Azure backlog attributed to power constraints
Meta$115–135BIncludes a 1GW Ohio facility and a Louisiana site scaling toward 5GW eventually
Oracle$50B+136% YoY; backed by $523B in remaining performance obligations

Industry Total & Trajectory

  • 2026: $660–690B combined, vs. ~$380B in 2025 — near-doubling in one year.
  • Allocation: AI compute, data centers, and networking.
  • Stargate (OpenAI/SoftBank/Oracle JV) targets $500B in AI infrastructure by 2029 — $100B initial deployment, >$400B in commitments inside the first three years.

Key Monitoring Points (per the author)

  1. Whether 2027 capex guidance keeps escalating or begins to plateau.
  2. Power infrastructure as the binding constraint on the pace of AI data-center deployment — echoed independently by the Fed's July 2026 MPR and the Data Center Knowledge power-bottleneck piece already in this KB.

Cross-Check Note

This figure ($660–690B) sits below the $725B total this KB's ai-hyperscaler-capex-2026 source (Value Add VC, ingested 2026-06-24) reported for the same five-company cohort — the range reflects genuine estimate dispersion across analysts (different treatment of Oracle, different FX/timing assumptions) rather than a correction. Treat $660–725B as the credible band for 2026 aggregate hyperscaler capex until a hyperscaler-reported aggregate (i.e., summed actual quarterly capex) closes the gap.