ANALYSIS2026-01-09·Latitude Media

Meta Strikes Up to 6.6 GW Nuclear Deal to Fuel Its AI Supercluster

Catherine Boudreau
COMPILED NOTES

Meta up to 6.6GW by 2035: Vistra 2.2GW+433MW, Oklo 1.2GW (2030), TerraPower 2.6GW+1.2GW storage (2032); no NRC permits yet

Meta's Up-to-6.6 GW Nuclear Deal

Core News

Meta contracted up to 6.6 GW of clean nuclear energy by 2035 to power its "Prometheus" AI supercluster in New Albany, Ohio — spanning existing plants (Vistra) and advanced reactors (Oklo, TerraPower).

Key Facts

  • Vistra: 2.2 GW existing Ohio nuclear + 433 MW incremental upgrades (Ohio/PA), 8-year window.
  • Oklo: Ohio campus, first reactors as early as 2030, target 1.2 GW.
  • TerraPower: up to eight Natrium reactors + storage; two online as soon as 2032; full 2.6 GW nuclear + 1.2 GW storage.
  • Neither Oklo nor TerraPower has NRC construction permits yet; TerraPower completed safety evaluation Dec 2025.
  • Scale ≈ northern Virginia's "Data Center Alley."

Entities

Meta (buyer); Vistra (existing nuclear operator); Oklo (SMR, DOE pilot); TerraPower (Gates-founded, Natrium).


Source: Meta strikes 6.6 GW nuclear deal — Catherine Boudreau, Latitude Media, 2026-01-09. Full-text fetched.