The grid interconnection queue is the binding constraint on the AI buildout — faster than capital, regulation, or fuel
Conviction
6.0/10
Trajectory
no history yetLast reviewed
—
Confidence: 8/10 Supporting evidence:
- 2,600 GW backlog, 5-year median wait — this is physical infrastructure time that cannot be compressed by money alone. Evidence: strong
- 80% of projects withdraw from the queue; even well-funded projects face uncertainty and cost. Evidence: strong
- Co-location (Amazon/Talen Susquehanna) is an attempted workaround; FERC outcome uncertain. Evidence: strong
Challenging evidence:
- PJM queue reform (April 2026) could meaningfully accelerate new interconnections to 1-2 years. Evidence: moderate — too early to verify
- HVDC transmission investment could expand capacity significantly by 2030. Evidence: moderate
Evolution:
- Jun 15, 2026 — Initial thesis at 8/10
Depends on: grid-interconnect-queue Would change if: FERC/PJM reforms demonstrably reduce interconnection time to <2 years at scale