Power and permission, not chips, now limit the US AI build

By MenFem Editorial·CoreWeave·Constellation Energy·Vistra·Oklo·Core Scientific·IREN·AI Infrastructure — Power and policy·6 November 2026·Methodology·
ai-infrastructurepowerpolicydatacentersthematic
The next review, the day it is written.
Share

What would prove this wrong · verbatim, as published

The reason for holding this stops being true if the build simply goes ahead: ERCOT's large loads approved to energise exceeding 19 GW (double the 9,456 MW of August 2026) by 6 Nov 2027. It also stops being true if the restraints fall away: by 6 Nov 2027, no statewide datacentre moratorium or permit hold in force anywhere in the US, with Texas's pause lifted. And it stops being true if power stops being short where the build is: PJM's 2029/30 capacity auction clearing below its price cap with no shortfall against the reliability requirement.
  • leg 1 · The build goes ahead: ERCOT large loads approved to energise above 19 GW by 6 Nov 2027 · not read yet
  • leg 2 · The restraints fall away: no statewide moratorium or permit hold in force by 6 Nov 2027, Texas's pause lifted · not read yet
  • leg 3 · Power stops being short: PJM 2029/30 clears below the cap with no reliability shortfall · not read yet

The argument, taken apart

Turn it, hover a ring, a moon or a weight
One call, taken apart
Rings are the falsifier’s legs. Moons are the catalysts it named. Weights are its risks, longer for higher severity.
The claim

After the 3 Nov elections the binding constraint on American datacentres is political: grid approvals, permits and who pays for power.

What would make it wrong · 3 legs
  1. Leg 1 · Not read yet
    The build goes ahead: ERCOT large loads approved to energise above 19 GW by 6 Nov 2027
    Not read at a review yet.
  2. Leg 2 · Not read yet
    The restraints fall away: no statewide moratorium or permit hold in force by 6 Nov 2027, Texas's pause lifted
    Not read at a review yet.
  3. Leg 3 · Not read yet
    Power stops being short: PJM 2029/30 clears below the cap with no reliability shortfall
    Not read at a review yet.
The window
6 Nov 2026 to 6 Nov 2027
0% gone · 365 days left
The reviews
Not reviewed since it was published
  • Leg 1, not read yet: The build goes ahead: ERCOT large loads approved to energise above 19 GW by 6 Nov 2027
  • Leg 2, not read yet: The restraints fall away: no statewide moratorium or permit hold in force by 6 Nov 2027, Texas's pause lifted
  • Leg 3, not read yet: Power stops being short: PJM 2029/30 clears below the cap with no reliability shortfall
  • ERCOT/PUC datacentre audit (filing targeted 10 Dec 2026)
  • PJM 2029/30 capacity auction (Dec 2026)
  • Texas 90th Legislature (from Jan 2027)
  • high severity: Paper queue
  • medium severity: Routing around grids

The timeline · 1 entry · newest firstreviews · notes · moves · the book

  1. 6 Nov 2026
    Opened

    Power and permission, not chips, now limit the US AI build

Key Points

  • Texas's grid-approval pause has pushed ERCOT's large-load study past April 2027.
  • 3 Nov: Texas, Ohio, Georgia and Wisconsin elected governors who back datacentre pauses.
  • New York's permit hold and Pennsylvania's bring-your-own-power order are in force.
  • PJM's last capacity auction cleared at the cap and 6.8 GW short of its reliability requirement.

For three years the question about the AI build was whether there would be enough chips. The question now is whether there will be enough permission. In Texas, the largest market for new datacentre load, the outgoing governor's August pause on grid approvals has already pushed ERCOT's large-load study past April 2027, and state environmental permits for datacentres are on hold until an audit is done. On 3 November Texas elected a governor who campaigned on a moratorium 'until a legislative session that puts Texans first', and governors-elect in Ohio, Georgia and Wisconsin back pauses of their own. New York already holds permits for large datacentres for up to a year; Pennsylvania now requires them to bring their own power and pay all costs. In PJM, the largest US grid, the last capacity auction cleared at its price cap and still came in 6.8 GW short of the reliability requirement. The claim is that over the next one to two years these restraints, not demand and not silicon, set the pace of US datacentre capacity, and that electricity already energised and contracted becomes the scarcest input in the stack. The strongest objections are stated in the falsifier: most of the Texas queue is speculative paper (9.5 GW approved to energise against 446 GW applied for), builders can route around grids with on-site gas, federal policy pushes for speed, and most of the new pledges are conditional and need legislatures to act. This thesis cuts against parts of MenFem's own book, and says so: IREN and Core Scientific are bullish calls on Texas capacity, and CoreWeave's bearish call is reinforced by it. Owners of plants that already run, such as Vistra and Constellation, can gain from the same scarcity. BULLISH on the thesis, conviction MEDIUM, one year. The direction is Connor's; the conviction is on MenFem's research recommendation.

Bull Case

Restraints spread: more states hold or condition approvals, Texas's pause runs into 2027, PJM stays short, and the price of energised, contracted power rises across the stack.

Bear Case

What I'd have to believe for the other side: elections make noise and grids get built anyway. The approved Texas pipeline is a fraction of the applications, the real projects are already moving, money finds the states that want it, and builders who cannot get a grid connection put a gas plant on site.

Catalysts

ERCOT/PUC datacentre audit (filing targeted 10 Dec 2026)Regulatory

Whether Texas's pause ends and when Batch Zero studies resume.

PJM 2029/30 capacity auction (Dec 2026)Regulatory

Clearing price and shortfall against the reliability requirement.

Texas 90th Legislature (from Jan 2027)Regulatory

Any datacentre statute or executive order under the new governor.

Risk factors

Paper queueHigh

If the restraints only cull speculative applications, the real build proceeds unchanged.

Routing around gridsMedium

On-site gas and federal sites could carry the build past state politics.

Related Calls

LONGActive

Debt-financed compute splits: matched loans hold, the rest reprice first

Loans backed by investment-grade contracts that run as long as the debt are holding. Loans that outlive their contracts are repricing, and they will break first.

Matched debt still prices as credit: IREN 5.96% (Microsoft-secured), Lambda 6.78% Baa1, Meta's SPV A+.

CoreWeave GPU loans: A3 at SOFR+2.25% (Mar) to Ba2/BB+ at SOFR+5.50% (Aug), ~5-year loans on ~3-year contracts.

ai-infrastructurefinancingneocloud
NVIDIAOracleCoreWeaveNebius GroupCore ScientificIREN