Economics of a Megawatt of AI Data Center
Fills the long-absent 'capex per MW' gap — the master unit of the buildout: ~$59M/MW all-in (~$30M IT + ~$29M infra), ~$15M/MW/yr lease revenue, ~$1M/MW opex, ~4yr payback. Unit economics as-of ~April 2025 (Crusoe CEO pricing), republished May 2026; single-operator estimate. Note divergent bases: shell-only ~$11.3M/MW, AI shell+fit-out ~$37.3M/MW.
Economics of a Megawatt of AI Data Center
Summary
Analysis piece (NextBigFuture, published 2026-05-02) that decomposes the cost and revenue of one megawatt of AI-data-center capacity. It fills the 'capex per MW — the master unit of the buildout, still absent' gap that has been open since the topic was created. The underlying unit economics are attributed to Crusoe CEO Chase Lochmiller's contract-pricing breakdown, dated ~April 2025 — so the figures are as-of ~April 2025, republished/analyzed May 2026. This is analysis-tier and rests on a single operator's pricing; treat the numbers as a labelled analyst estimate, not fact.
Key figures (unit economics as-of ~April 2025, per Crusoe; republished May 2026)
Capex — all-in ~$59M per MW of developed capacity
- IT (GPUs, CPUs, networking, storage): ~$30M/MW — i.e., roughly half the all-in is the compute inside the building, not the building.
- Infrastructure (datacenter shell, power plant/generation, other): ~$29M/MW.
Revenue — ~$15M+ per MW per year
- Pure infrastructure lease / IaaS layer: ~$15M/MW/yr
- Managed-services / cloud layer: an additional ~$15M+/MW/yr possible → combined ~$30M+/MW/yr
Opex & returns
- Annual opex (power + other): ~$1.0–1.1M/MW
- Annual net revenue from infrastructure alone: $1M+/MW
- Payback: ~4 years on the infrastructure investment.
Cross-check against other 2026 $/MW estimates (from search, NOT ingested)
The $/MW figure is contested and definition-dependent — capturing the spread so the number isn't quoted as a point:
- Aggregator benchmarks put standard DC construction at ~$11.3M/MW (2026, shell) and AI-optimized all-in at ~$37.3M/MW (shell + ~$25M/MW tech fit-out).
- This source's ~$59M/MW all-in is higher because it bundles on-site power generation and a fuller IT load.
- The definition drives the number: shell-only ($10–12M) < AI shell+fit-out (
$37M) < all-in incl. on-site generation & full IT ($59M). Always state which basis when quoting.
On-thesis relevance
The capex/MW figure is what lets the whole buildout be modelled end-to-end — it converts the hyperscaler capex aggregates ($610–725B) and the neocloud capex (CoreWeave $31–35B/yr) into deliverable megawatts, and it ties to the grid-queue and rack-power sources (135 kW/rack → ~7.4 racks/MW). The ~half-is-IT split is the key insight: it means capex tracks GPU shipments (hence CoWoS/HBM bind capex directly), and the ~4yr payback / ~$15M/MW/yr lease is the direct input to frontier debate #2 (do neoclouds earn their cost of capital, or is it a depreciation mirage?).
Provenance / caveats
- Single-operator pricing (Crusoe), analyst-republished — the weakest provenance among this ingest batch. Numbers are an estimate labelled as such.
- The revenue/payback figures assume full utilization and the operator's own contract pricing; they are best-case unit economics, not a realized cohort average.
- As-of basis is ~April 2025 for the unit economics despite the May 2026 publication — GPU prices and $/MW have moved since.
Source: Economics of a Megawatt of AI Data Center, NextBigFuture, 2026-05-02 (unit economics per Crusoe CEO, ~April 2025).