Anthropic signs a 20-year lease for ~401 MW at TeraWulf's Justified Data campus in Hawesville, Kentucky, ~$19B of contracted revenue

Signed · announced 6 Jul 2026 · the week to 10 Jul 2026

Size
$19B
Power
401 MW
Term
20 years

The parties

The source

TeraWulf 8-K Ex. 99.1, 2026-07-06Regulatory filing

Developed in phases; initial capacity in service H2 2027, full 401 MW by early 2028. TeraWulf says the lease is expected to be supported by an investment-grade credit. Signed directly with Anthropic, not via Fluidstack.