Compute · the Ledger · Site lease

AMD leases 377 MW from Core Scientific for 15 years and backs 152 MW of neocloud leases, with rights to ~1.9 GW more

Signed · announced 28 Jul 2026 · the week to 31 Jul 2026

Size
undisclosed
Power
529 MW
Term
15 years · to 27 Jul 2041

Core Scientific: more than $14B of potential base contracted revenue across ~530 MW at five sites.

The parties

The source

Core Scientific 8-K, 2026-07-28Regulatory filing

AMD leases at Pecos TX, Muskogee OK and Hunt County TX; an unnamed neocloud leases 152 MW at Auburn AL and Dalton GA with AMD credit support (AMD may cure defaults). AMD holds a reservation right on 1,925 MW more through 2028-12-28 (up to 2.5 GW total) and receives market-priced Core Scientific warrants. Three five-year options. Accelerator as stated: AMD Instinct.