The Markets Desk — Week 46 · Wed 11 Nov 2026
Compute · the Ledger · Site lease

TeraWulf and Fluidstack form a JV for a 168 MW Abernathy, Texas campus under a 25-year, ~$9.5B lease; Google backstops $1.3B

Signed · announced 28 Oct 2025 · the week to 31 Oct 2025

Size
$9.5B
Power
168 MW
Term
25 years

The parties

The source

TeraWulf 8-K Ex. 99.1, 2025-10-28Regulatory filing

TeraWulf 50.1% (rising to 51%), Fluidstack 49.9%. Serves 'a global hyperscale AI platform developing frontier-scale foundation models'. Delivery expected H2 2026. On 2026-07-06 TeraWulf agreed to sell its entire 50.1% interest to an investor group led by Fluidstack (TeraWulf 8-K Ex. 99.1, 2026-07-06).

The same parties, other deals