The Markets Desk — Week 45 · Thu 5 Nov 2026
Compute / Build-out · week to 4 Sept 2026

The build-out, floor by floor, one week at a time.

From models at the top to permits at the bottom: what switched on, what was announced and what got stuck in the week from 29 Aug 2026 to 4 Sept 2026. Every mark is a dated row with its source.

A model of an AI campus hall, its copper gantry crane over rows of machines.
The build-out mapRows, never forecasts
Switched on
Data centres 1
Announced
Optics 1
Stuck
Models and demand 1 · Power and grid (context) 3 · gone quiet: State commercial power sales
Biggest constraint move
Grid equipment prices: gas-steam-turbines 173.801 index, December 2003 = 100
Next due
Barber Lake · "by September 2026"
This week
1 · 1 · 4
switched on · announced · stuck, counted per floor and never added across families · 6 series not read
Hover or tap
Each floor is a layer of the build-out; each mark one dated row of the week
Solid: switched on, as filed or measured. Hollow: announced. Hanging: stuck. A faint stub: a series we list but cannot read.

Models and demand

  • Model retirements: google · 1 in the week (2026-08-31)

Money

  • Data-centre debt filed: not collected

Compute market

    Accelerators and fab

      Memory

      • HBM statements: kept by hand
      • Korean memory exports: key parked

      Optics

      • Optics backlog: CIEN (2026-09-03)

      Data centres

      • Data-centre construction spend: data-center-saar 96,462 USD millions SAAR (2026-09-01)

      Power and grid (context)

      • Grid equipment prices: gas-steam-turbines 173.801 index, December 2003 = 100 (2026-09-01)
      • Grid equipment prices: transformers 475.065 index, June 1981 = 100 (2026-09-01)
      • Grid equipment prices: turbines 289.639 index, June 1982 = 100 (2026-09-01)
      • State commercial power sales: stale
      • Transformer and turbine imports: key parked

      Permits and land

      • Local votes against: kept by hand

      Floor by floor

      Models and demand

      Money

      Nothing filed this week.

      Not read this week: Data-centre debt filed (not collected)

      Compute market

      Nothing filed this week.

      Accelerators and fab

      Nothing filed this week.

      Memory

      Nothing filed this week.

      Not read this week: HBM statements (kept by hand) · Korean memory exports (key parked)

      Optics

      Announced · 1

      Data centres

      Power and grid (context)

      Not read this week: State commercial power sales (stale) · Transformer and turbine imports (key parked)

      Permits and land

      Nothing filed this week.

      Not read this week: Local votes against (kept by hand)

      The pipeline, Texas · three ladders, never added

      What the campuses filed, what ERCOT counts in its own queue, and what Epoch estimates. Each is its own family, kept apart.

      Filed as energized
      0 MW
      across the 7 Texas campuses on the register
      Promised by now, not yet filed
      none
      Campus · stage
      Hover or tap a bar
      Solid is filed as happened; hollow is promised. Height is the largest stated figure; each basis is listed apart, never added.
      • Abernathy: Contracted: 240 MW gross, 168 MW critical IT, filed 28 Oct 2025; Delivered: 168 MW critical IT, promised in the second half of 2026
      • Barber Lake: Contracted: 244 MW up to (a ceiling), 168 MW critical IT, filed 25 Sept 2025; Delivered: 168 MW critical IT, promised by September 2026
      • Beacon Point: Contracted: 352 MW IT load, filed 6 May 2026
      • CoreWeave Denton: Contracted: 260 MW critical IT, filed 27 Feb 2025
      • Helios: Contracted: 526 MW critical IT, filed 5 Aug 2025; Delivered: 200 MW gross, 133 MW critical IT, filed 5 Aug 2026; Delivered: 260 MW critical IT, promised 2027
      • IREN Childress: Contracted: 200 MW IT load, 60 MW up to (a ceiling), filed 7 May 2026; Delivered: no megawatts stated, promised by year-end
      • Stargate Abilene: Under construction: 1,200 MW basis unstated, filed 21 May 2025; Energized: 1,200 MW basis unstated, promised in mid-2026
      Drawn against asked
      5,900 MW / 321,000 MW
      Observed energized (13 May 2026) against no studies submitted (13 May 2026). ERCOT's own buckets, each at its own date.
      Bucket
      Hover or tap a ring
      Each ring's area is its megawatts. Buckets are ERCOT's own, separate counts, not a running total.
      • No studies submitted: 321,000 MW, ERCOT, 13 May 2026
      • Under ERCOT review: 93,700 MW, ERCOT, 13 May 2026
      • §9.5 requirements met: 22,000 MW, ERCOT, 13 May 2026
      • Approval to energize: 9,042 MW, ERCOT, 12 Mar 2026
      • Observed energized: 5,900 MW, ERCOT, 13 May 2026
      Epoch’s estimate
      —
      Not read yet: the first Epoch AI snapshot

      Demand meter · each grid against itself a year earlier

      Electricity each grid operator served in the week to 4 Sept 2026, from EIA’s hourly grid data, against the same seven days a year earlier. Weather moves these from week to week, so a change on the year is not all data centres. Each grid is its own figure; none is added to another.

      • PJM (Mid-Atlantic and northern Virginia)19,446 GWh+33.0%
      • ERCOT (Texas)12,065 GWh+15.0%
      • Southern Company (Georgia and Alabama)5,812 GWh+23.2%
      • MISO (Midwest)15,700 GWh+27.3%
      • Tennessee Valley Authority4,141 GWh+27.4%
      • Duke Energy Carolinas2,624 GWh+33.8%
      • Southwest Power Pool7,606 GWh+36.2%
      • Arizona Public Service1,019 GWh+6.1%

      Power sold to commercial customers, August 2026

      The closest public read of data-centre load, from EIA’s monthly survey of utilities. It lands about two months after the month it counts.

      • Virginia8,503 GWh+0.5%
      • Texas18,258 GWh+7.8%
      • Georgia6,132 GWh+13.2%
      • Ohio6,010 GWh+8.4%
      • Arizona4,548 GWh+12.3%
      Henry Hub gas
      $2.95 per MMBtu
      September 2026 average, from EIA’s Short-Term Energy Outlook · −0.7% on the year. The fuel behind most new generation: context only.
      Gas generation due in 2026-06 that arrived on time (EIA-860M)
      Turbine backlogLast reading 28 Oct 2026
      Grid equipment pricesLast reading 1 Sept 2026
      Weekly grid demandLast reading 30 Oct 2026
      State commercial power salesLast reading 1 Aug 2026
      Henry Hub gas priceLast reading 1 Sept 2026
      Transformer and turbine importskey parked
      Local votes againstkept by hand

      What the map reads, and how fresh it is

      • Model releases4 Nov 2026fresh
      • Provider incidents5 Nov 2026fresh
      • Model retirements14 May 2028fresh
      • Data-centre debt filed—not collected
      • Taiwan monthly revenue1 Sept 2026fresh
      • MLPerf rounds16 Sept 2026fresh
      • Export controls20 Nov 2026fresh
      • HBM statements—kept by hand
      • Korean memory exports—key parked
      • Optics backlog3 Sept 2026fresh
      • Data-centre construction spend1 Sept 2026fresh
      • Turbine backlog28 Oct 2026fresh
      • Grid equipment prices1 Sept 2026fresh
      • Weekly grid demand30 Oct 2026fresh
      • State commercial power sales1 Aug 2026stale
      • Henry Hub gas price1 Sept 2026fresh
      • Transformer and turbine imports—key parked
      • Local votes against—kept by hand

      How the map is kept

      • The week runs Saturday to Friday, the same week as the compute board.
      • Switched on means filed or measured: a filing that says energized or delivered, a price the Tape wrote, a figure a statistics office published.
      • Announced means a promise, an order or a deal: hollow until something switches on.
      • Stuck means a date moved, a promise came due unmet, a price feed went quiet, or a rule or vote added a constraint.
      • Filed figures, ERCOT’s meter, Epoch’s estimate and EIA’s generator data are separate families and are never added together.
      • A floor with no rows says so. A series we list but cannot read shows as not read, with the reason.
      • Power and the grid are here as context for the build-out. Nothing on this page is a trade idea.