Fluidstack leases >200 MW at TeraWulf's Lake Mariner campus for 10 years, ~$3.7B of contracted revenue

Signed · announced 14 Aug 2025 · the week to 15 Aug 2025

Size
$3.7B
Power
200 MW
Term
10 years · to 13 Aug 2035

~$3.7B over the initial 10-year terms; ~$8.7B with two five-year extensions. MW is 'more than 200'.

The parties

The source

TeraWulf 8-K Ex. 99.1, 2025-08-14Regulatory filing

Two leases (CB-3, CB-4) in Barker, New York, delivered in two phases in 2026. Google backstop: see google-terawulf-backstop-2025-08. On 2025-08-17 Fluidstack added the 160 MW CB-5 building on the same terms, taking its Lake Mariner total to ~360 MW (8-K 2025-08-18).